$122 billion in new cost growth: Weapons programs that went over budget this year

In one year, 46 of the Pentagon's biggest weapons programs reported $122 billion in cost increases. The average new system now takes over 12 years to deliver.

FraudBadPublic receipt
Department of Defense
  1. Planned spend on the costliest weapons programsOver $2.4 trillion2
  2. Programs reporting cost increases46 of 722
  3. Total of those increases$122B2
  4. Programs reporting decreases16, totaling $47B2
  5. Average time to deliver a new capabilityOver 12 years2
  6. Penalty for going over████████████████
fraudbad.comNo taxation without receipts

What happened

GAO's 2026 annual review of the Pentagon's major weapons programs found 46 of 72 programs reported cost increases totaling $122 billion, against $47 billion in decreases elsewhere.

The department plans to spend more than $2.4 trillion on these programs. The average time to field a new capability rose to more than 12 years.

Why nobody caught it

  • Cost growth is reported every year, and the programs continue.

How sure are we?

Over budget

Officially measured cost growth or delay beyond what was promised.

Measured by GAO from the Pentagon's own program data. Cost growth isn't fraud; it's money spent beyond what Congress was told.

Sources

  1. GAO-26-108457: Weapon systems annual assessmentU.S. Government Accountability Office · Jul 2026

Spot an error? Send the source and we'll fix it.

America.co · The RECEIPTS Act

Want to stop it?Sign the Receipts Act.

Public money should come with a receipt anyone can check. The RECEIPTS Act starts with one rule for federal purchases over $25,000 from GSA's buying catalog: publish the price paid next to what other agencies paid for the same thing.

Sign the Receipts Act ↗

A citizen-authored working draft hosted on America.co. It has not been introduced in Congress.